Objectives
After successfully completing the course, the participants will be better able to
- Specify the General Requirements for Frame, Tube & Clamp, and System Scaffolds.
- Determine the hazards associated during erection, dismantling, altering and using of scaffolds.
- Determine the Specific Safety Rules and Steps Associated with the Erection of Frame, Tube & Clamp and System Scaffolding.
- Identify the Major Items to Consider when Performing a Scaffold Inspection.
- Specify the Major Elements of OSHA's Regulation 29 CFR Subpart L - Scaffolding.
- Design and calculate the scaffold loads
Outlines
DAY ONE:
- 8:00-8:30 Registration & Coffee
- 8:30-9:00 History of Scaffolds Accidents
- 9:00-09:30 Definitions
- Scaffold Competent Person
- Scaffold Qualified Person
- What is Scaffold
- Parts of Scaffolds
- 09:30-09:45 Break
- 09:45-10:45 Types of Scaffolds
- Frame Scaffolds
- Tube & Clamp Scaffolds
- Modular Scaffolds
- Suspended Scaffolds
- Bracket Scaffolds
- Mobile Scaffolds
- 10:45-11:00 Break
- 11:00-12:00 Scaffolding Work Preparation
- 12:00-12:45 Prayer Break
- 12:45- 14:00 Hazards of Scaffolds
- 14:00 End of Day One
DAY TWO:
- 8:00-8:15 Coffee
- 8:15-8:45 Review of Day 1
- 8:45-10:30 Hazards of Scaffolds and General Safety Requirements (Continuation)
- Scaffolds Ladders
- Falling Objects
- Electrocution (Dealing with overhead power lines)
- Bad Planking Give Away
- 10:30-10:45 Break
- 10:45-12:00 General Safety Requirements
- Scaffolds Platforms and Planks requirements
- 12:00-12:45 Prayer Break
- 12:45-14:00 General Safety Requirements (Continuation)
- Securing of Scaffolds against Collapse (Ties-Guys, etc.)
- Scaffold Foundation
- Plumb, Level, and Square of Scaffolds
- 14:00 End of Day Two
DAY THREE:
- 8:00-8:15 Coffee
- 8:15-8:45 Review of Day 2
- 8:45-9:45 Safe Method of Erection & Dismantling of Scaffolds
- 9:45-10:30 Scaffold Inspection
- 10:30-10:45 Break
- 10:45-11:15 Training Video
- 11:15-12:00 Mobile & Suspended Scaffolds- Aerial Lifts
- 12:00-12:45 Prayer Break
- 12:45-13:15 Under hung Scaffold
- 13:15-14:00 Scaffold Loading
- Types of Scaffold Loading
- Introduction to Scaffold Load Calculations
- 14:00 End of Day Three
DAY FOUR:
- 8:00-8:15 Coffee
- 8:15-8:45 Review of Day 3
- 8:45-10:00 Scaffold Load Calculations
- 10:00-10:30 Different Exercises
- 10:30-10:45 Break
- 10:45-12:00 MCQ TEST (Multiple Choices Questions Test)
- 12:00-12:45 Prayer Break
- 12:45-14:00 Correcting & Reviewing of MCQ Test
- 14:00 End of Day Four
DAY Five:
- 8:00-8:15 Coffee
- 8:15-8:30 Review of Day 4 and prepare for practical training
- 8:45-12:00 Practical Training onsite
- 12:00-13:00 Prayer Break
- 13:00-13:30 Ending of Training
Who Should Attend
- Construction Forman & Supervisors
- Scaffold Technician
- Construction Engineers
- Safety Engineers, Supervisors and Officers